Blast Furnace, Mini Blast Furnace and Pig Iron Plants

Tata Steel Ltd
  • Detailed project report to be followed by design and engineering services for the phase III modernisation programme
  • Consultancy services for installation of 4th stove for G blast furnace
  • Total consultancy services as part of 1 MTPA expansion including project report, detailed engineering, procurement, inspection, project management, progress monitoring, cost control & budgeting, construction planning, detailed site supervision and commissioning assistance for G blast furnace upgradation
  • Consultancy services for ‘F’ blast furnace upgradation project at Jamshedpur
  • Detailed design and engineering services for modernisation phase III of Jamshedpur works
  • Engineering services for installation of special purpose probes in ‘G’ blast furnace at Jamshedpur
  • Engineering services for screening of iron ore for A to F blast furnaces at Jamshedpur
  • Detailed engineering services for 1 MTPA G blast furnace upgradation
  • Engineering services for relining of ‘E’ blast furnace
  • Engineering services for hearth repair of ‘B’ blast furnace.
  • Engineering services for hearth repair of ‘D’ blast furnace.
  • Engineering services for rebuilding of ‘F’ blast furnace.
  • Engineering services for installation of ‘G’ blast furnace.
  • Detailed engineering services for G blast furnace and coal injection plant of D & F blast furnace
  • Total consultancy services for 6.8 MTPA growth plan including project report, detailed engineering, procurement, inspection, project management, progress monitoring, cost control & budgeting, construction planning, detailed site supervision and commissioning assistance for ‘H’ blast furnace and sinter plant-4
Rourkela Steel Plant, Rourkela / Steel Authority of India Ltd (SAIL)
  • Preliminary civil designs for blast furnaces and steel melt shop at Rourkela steel plant, Orissa
  • Detailed project report followed by comprehensive design and engineering services for modernisation of Rourkela Steel Plant (Capacity after modernisation: 1.9 million tons/year). Dasturco also prepared the Environmental Impact Assessment (EIA) study and the Environmental Management Plan (EMP).
Durgapur Steel Plant, Durgapur / Steel Authority of India Ltd (SAIL)
  • Report on study of logistic problems in the charging side of blast furnaces
Visakhapatnam Steel Plant / Rashtriya Ispat Nigam Ltd
  • Feasibility report on category-I capital repair of BF-1
Maharashtra Electrosmelt Ltd, Nagpur
  • Design, engineering and construction supervision services for ferromanganese and pig iron plant, Nagpur
J.K. Industries Ltd, New Delhi
  • Design and engineering consultancy services for pig iron plant to be located in Madhya Pradesh (capacity: 225,000 tons/year of foundry grade pig iron)
NECO Industries Ltd
  • Comprehensive design and engineering services for mini-steel plant, Siltara, Raipur district, Chattisgarh. (based on mini-blast furnace and BOF converters) (capacity: 350,000 tons/year of foundry grade pig iron).
MESCO Kalinga Steel Ltd, Orissa
  • Consulting engineering services for integrated steel plant (capacity: 2.25 million tons/year of hot rolled coils) based on the BF-BOF route to be located at Jajpur in Orissa.
Southern Iron and Steel Company Ltd., Tamil Nadu
  • Design and engineering services for BF-based steel project, Macheri, Salem (capacity: 260,000 tons/year of liquid steel to produce 130 mm and 160 mm sq billets). Forward integration of the mini BF pig iron plant.
  • Basic engineering, detailed design and engineering, project monitoring, site supervision, inspection and expediting etc for forward integration of the BF plant - rolling mill (capacity: 230,000 tons/year of mild steel and alloy steel bars and rods)
Bellary Steels and Alloys Ltd, Karnataka
  • Basic and detailed engineering; procurement services; project monitoring/ management; construction supervision, inspection and quality assurance etc for integrated steel projects based on BF-BOF-CC route, Bellary (capacity : 0.5 million tons/year of bars and rods). Major facilities includes sinter plant (130 sw m); blast furnace (650 cu m); 2x50 ton BOF units; a 4-strand CC billet caster; and a bar and rod mill.
Ispat Metallics India Ltd
  • Detailed engineering and technical services for the installation of the blast furnace plant of blast furnace project, Dolvi, Maharashtra (capacity: 1.8 million tons/ year)
  • Detailed engineering services for blast furnace and auxiliary plants at Dolvi
  • Engineering services for coal injection plant at Dolvi
Ispat Industries Ltd, Maharashtra
  • Detailed engineering and consultancy services for oil injection plant at Dolvi.
  • Feasibility report on rebuilding of blast furnace